Large Projects Bio-Mass Power

BIOMASS POWER PROJECTS

Punjab is predominantly rich in agriculture and contributes the major share to the grain basket of India. It has surplus production of major crops. It produces 25% of country’s cotton, 22% of wheat and 55% of rice, even though it has only 1.5% of total country cultivable area. Punjab has been meeting its electrical power requirements primarily through conventional thermal and hydro power generation. Hydro power generation has a tendency to fluctuate depending on the availability of water. Thermal power generation has to depend on coal which has to be transported from eastern part of India involving large distances. Cost of generation from coal continuous to escalate and moreover it is polluting.

Biomass Power project has the following inherent advantages over thermal power generation :

    1. It is environmentally friendly because of relatively lower CO2 and particulate emissions
    2. It  displaces fossil fuels such as coal
    3. It is a decentralised, load based means of generation, because it is produced and consumed locally, losses associated with transmission and distribution are reduced
    4. It offers employment opportunities to locals
    5. It has a low gestation period and low capital investment
    6. It helps in local revenue generation and upliftment of the rural population
    7. It is an established and commercially viable technology option.
    8. Punjab has substantial availability of Biomass / Agrowaste in the state is sufficient to produce about 1000 MW of electricity. PEDA has planned to develop some of the available potential talukas / tehsils with the aim to promote and install biomass / agro waste based projects. PEDA has so far allocated 30 sites / tehsils for setting up of total 332.5 MW capacity Biomass / Agrowaste based power projects under three phases.

(A) BIOMASS POWER PROJECTS COMMISSIONED IN THE STATE BY PEDA :

S.No.

Name of the Company

SITE

CAPCITY

01

M/s Malwa Power Ltd.

Vill. Gulabewala, Distt. Mukatsar

6MW

02

M/s Dee Development Engineers Pvt. Ltd

Vill.Gadda Dhob, Tehsil. Abohar Distt Ferozepur

8MW



(B) ON GOING BIOMASS POWER PROJECTS ON BOO BASIS

Total No. of Sites : 27 . Total Capacity: 282 MW
Phase I-56MW.
Phase II-10MW (Project of 31MW cancelled).
Phase III-226MW.
Projects under Phase – I (56 MW)


M/S. Turboatom-TPS Projects Pvt. Ltd.

S.No.

Name of Site(Tehsil)

Cap. (MW)

Likely Date of comm..

1

 Vill. Booh, Patti (Amritsar)

10

Dec, 2010

2

Vill. Kot Majlis, Batala (Gurdaspur)

10

Dec, 2010

3

 Vill. Burj Baghel Singh, Malerkotla (Sangrur)

20

Dec, 2010

4

Vill. Jhok Tehal Singh, Ferozepur (Ferozepur)

10

Dec, 2010


M/s. Green Field Energen Pvt. Ltd. (Energen)

S.No

Name of Site(Tehsil)

Cap.(MW)

Expected Date of comm..

5

 Talwandi Sabo

6

Dec, 2010



Projects under Phase – II (10 MW)

M/S Sea Sky Cargo & travels Pvt. Ltd.

S.No.

Name of Site(Tehsil)

Cap (MW)

Expected Date of commissioning

1

 Ajnala (Amritsar)

10

Dec, 2010


M/s  Menakshi Infrastructure Pvt Ltd (CANCELLED)

S.No.

Name of Site(Tehsil)

Capacity (MW)

Expected Date of commissioning

2

Sunam (Sangrur)

31

Dec, 2010


Projects under Phase – III ( 226 MW)


M/S. Green Planet Energy Pvt Ltd.

S.No.

Name of Site (Tehsil)

Cap. (MW)

Likely Date of commissioning

1

MVill. Manuke Gill, Tehsil Nihal Singh Wala & Bagha Purana, Distt. Moga

6

Dec., 2010

2

Vill. Bir Pind, Tehsil Nakodar, Distt. Jalandhar

10

Dec., 2010

3

Vill. Deep Singh Wala, Tehsil & Distt. Faridkot

9

Dec., 2010

4

 Vill. Ramiana, Tehsil Jaito, Distt. Faridkot

13

Dec., 2010

5

Vill. Binjon, Tehsil Garhshankar, Distt. Hoshiarpur

10

Dec., 2010

6

 Vill. Talwandi Rai, Tehsil Raikot, Distt. Ludhiana

14

Dec., 2010

7

 Vill. Handiyan, Teh. & Distt. Barnala

10

Dec., 2010

8

 Phillour, Distt. Jalandhar

10

Dec., 2010

9

Shahkot, Distt. Jalandhar

10

Dec., 2010

10

 Vill. Kalyan Sukha, Teh & Distt. Bathinda

13.5

Dec., 2010

11

 Vill. Dhanasoo, Tel & Distt. Ludhiana

15

Dec., 2010

12

 Vill. Challaiwala, Teh Sultanpur Lodhi, Distt. Kapurthala

9

Dec., 2010

13

 Vill. Boran, Teh & Distt. Fatehgarh Sahib

11

Dec., 2010

14

 Vill. Kanhari, Tehsil  Amloh & Distt. Fatehgarh Sahib

6

Dec., 2010


M/S. Universal Biomass Energy Pvt. Ltd.

S.No.

Name of Site

Cap.  (MW)

Expected Date of comm..

1

. Malout (Closer to Mandi Dabwali)

14.5

Dec., 2009

M/S. Food Fats & Fertilizers Pvt. Ltd,

S.No.

Name of Site(Tehsil)

Capacity (MW)

Expected Date of comm..

1

 Mansa

20

Dec., 2010

M/S. P & R Engineering Services Ltd.

S.No.

Name of Site(Tehsil)

Capacity (MW)

Expected Date of comm..

1

Anandpur Sahib

5

Dec., 2010

2

Ropar

10

Dec., 2010

3

 Nawanshahr

10

Dec., 2010


M/s Orient Green Power Pvt. Ltd

S.No.

Name of site (Tehsil)

Cap. (MW)

Expected Date of Comm..

1

 Amritsar

10

Dec., 2010

2.

 Patiala

10

Dec., 2010

 

 

(A)       Actions completed  (A) BIOMASS POWER PROJECTS COMMISSIONED IN THE STATE BY PEDA : (28.5 MW)


S.No.

Name of the Company

SITE

CAPCITY

Month of Commissioning

Remarks

01

M/s Malwa Power Ltd.

Vill. Gulabewala, Distt. Mukatsar

6 MW

May, 2005

First project allocated by PEDA

02

M/s Dee Development Engineers Pvt. Ltd

Vill.Gadda Dhob, Tehsil. Abohar Distt Ferozepur

8 MW

Feb., 2009

Project was allocated under Phase - II

03

M/s Universal Biomass Energy Pvt. Ltd.

Vill. Channu The. Malout

14.5 MW

Oct., 2009

Project was allocated under Phase - III

 

 

 

 

 

 

 

 

 

(B)       Actions under Completion :  ON - GOING BIOMASS POWER PROJECTS ON BOO BASIS
Total No. of Sites : 25 . Total Capacity: 267.5 MW
Phase I-          56 MW.  (5Nos.)         (Excluding one Project of 10 MW cancelled)
Phase II-         Nil       (Two Projects of 31 MW & 10 MW cancelled & one project of 8 MW commissioned)).
Phase III-        211.5 MW (20 Nos.). (Excluding one project of 14.5 MW commissioned.)
Projects under Phase – I (56 MW)                       ( Date of allocation : 1.11.2005 ) Original Scheduled date of Commissioning: 10.9.2007
M/S. Turboatom-TPS Projects Pvt. Ltd.

S.No.

Name of Site(Tehsil)

Cap. (MW)

Status

Decision taken in the meeting on 27.7.2010

Remarks

Actions completed                                          Actions under Completion

1

 Vill. Booh, Patti (Amritsar)

10

.11Acre 6 Kanal Panchayat Land lease agreement papers  submitted.
MoU signed on 25.11.2005.
DPR approved
IA signed on 24th May, 2010.
PPA with Powercom signed on 3.8.2010.

Construction at site yet to start.

 

  • Company was asked to sign PPA with Powercom.
  • Company committed to commission the project by Dec., 2011.
  • Progress to be reviewed in Oct., 2010.
  • Asked Company to achieve Financial closure by Aug., 2010

 

Overall delay of
4 years 4 month approx. as on 31st August., 2010

 

Enhanced Security partially deposited.
Balance Rs. 12.50 Lacs yet to be deposited.

Revised extension granted for 15 months   completion by Sep., 10

2

Vill. Kot Majlis, Batala (Gurdaspur)

10

MoU signed on 25.11.2005.
30 days termination notice given on 4.6.2010

Draft DPR, –Submitted, Pending evaluation & approval.
Land still not acquired and land papers yet to be submitted.
Clearances yet to be obtained. IA & PPA not signed.

- Batala site is to be reviewed only if progress is satisfactory in Patti & Ferozepur.

3

 Vill. Burj Baghel Singh, Malerkotla (Sangrur)

20

10 Acre Panchayat Land lease agreement papers submitted on 20.1.2009. MoU signed on 25.11.2005
DPR approved. SCA cum SAC clearance & Ground water clearance & CLU granted.
Feasibility clearance from PSEB received.
30 days termination notice given on 4.6.2010

IA & PPA yet to be signed.

  • Malerkotla site is to be reviewed only if progress is satisfactory in Patti & Ferozepur.
  • Company was asked to submitted the balance enhanced performance security of Rs. 12.5 lacs immediately.

4

Vill. Jhok Tehal Singh, Ferozepur (Ferozepur)

10

10 Acre Panchayat Land lease agreement papers  submitted
DPR approved. MoU signed on 25.11.2005.

IA signed on 24th May, 2010.
PPA   with Powercom signed on 3.8.2010.

 

Construction at site yet to start.

  • Company was asked to achieve Financial closure by Aug., 2010
  • Company committed to commission the project by Dec., 2011.
  • Progress to be reviewed in Oct., 2010.

 

M/s. Green Field Energen Pvt. Ltd. (Energen)

S.No

Name of Site(Tehsil)

Cap.
(MW)

Status

Decision taken in the meeting on 27.7.2010

Remarks

Actions completed                                          Actions under Completion

5

 Talwandi Sabo

 

6

MoU signed on 5.12.2005.
Land registration papers for 6 Acre 7 Kanal land submitted.

30 days termination notice given on 4.6.2010

DPR for 6 MW submitted after much delay on 17.8.2010

IA & PPA yet to be signed.

SCA-cum-SAC clearance received in June, 2010.
CLU clearance received in April, 2010.

  •  Progress to be reviewed in Oct., 2010.

 

Overall delay of
4 years 4 month approx. as on 31st August., 2010

 

Enhanced Security deposited.
Revised extension granted for 15 months   completion by Sep., 10

 

Projects under Phase – II – One project of 8MW cap. Commissioned.

Projects under Phase – III ( 211.5 MW) ( Date of allocation : 15.10.2007 ) Original Scheduled date of Commissioning: 25.8.2009

M/S. Green Planet Energy Pvt Ltd.

S.No

Name of Site (Tehsil)

Cap. (MW)

Status

Decision taken in the meeting on 27.7.2010

Remarks

Actions completed                                          Actions under Completion

1

Vill. Manuke Gill, Tehsil Nihal Singh Wala & Bagha Purana, Distt. Moga

6

24 Acre 3 Kanal 18 Marle panchayat land on lease for 33 years. MoU & IA signed.  PPA signed on 14.10.2009.

All statutory clearances obtained

Civil Construction Work in progress.

Boundry pillars, office construction completed.
Expected date of Commissioning in July, 2011

  • Asked company to achieve financial closure immediately
  • Company to report every month about the progress.
  • Commissioning date to remain uptill Dec., 2011.

Overall delay of 2 years 4 month approx. as on 31st August., 2010

Enhanced Security deposited.

Revised extension granted for 15 months  completion by Sep., 10

2

Vill. Bir Pind, Tehsil Nakodar, Distt. Jalandhar

10

30 Acre panchayat land on lease for 33 years MoU & IA signed. PPA signed on 14.10.2009.

All statutory clearances obtained

Civil Construction Work in progress
Boundry pillars, office construction completed.
Civil works of boiler, T.G. Building, cooling tower digesters, internal roads, auxiliary buildings & weigh bridge under progress
Expected date of Commissioning in Dec. 2010

  • Asked company to achieve financial closure immediately
  • Company to report every month about the progress.
  • Commissioning date to remain uptill Dec., 2011

3

Vill. Deep Singh Wala, Tehsil & Distt. Faridkot

9

30 Acre 5 Kanal 6 Marle panchayat land on lease for 33 years
MoU & IA signed. PPA signed on 14.10.2009.

All statutory clearances obtained

Civil Construction Work held up due to high water table.

Boundry pillars completed.
Expected date of Commissioning in Dec. 2011

  • Asked company to achieve financial closure immediately
  • Company to report every month about the progress.
  • Commissioning date to remain uptill Dec., 2011

4

 Vill. Ramiana, Tehsil Jaito, Distt. Faridkot

13

15 Acre 5 Kanal 12 Marle panchayat land on lease for 33 years
MoU & IA signed. PPA signed on 14.10.2009.

All statutory clearances obtained

Boundry pillars completed
Expected date of Commissionning inDec. 2011

  • Asked company to achieve financial closure immediately
  • Company to report every month about the progress.
  • Commissioning date to remain uptill Dec., 2011

5

Vill. Binjon, Tehsil Garhshankar, Distt. Hoshiarpur

10

24 Acre 5 Kanal 2 Marle panchayat land on lease for 33 years.
MoU & IA signed. PPA signed on 14.10.2009.

 

All statutory clearances obtained

Construction Work in progress.

Boundry pillars, office construction completed
Civil works of boiler, T.G. Building, cooling tower digesters, internal roads, auxiliary buildings & weigh bridge under progress.
Expected date of Commissioning in Nov. 2010

  • Asked company to achieve financial closure immediately
  • Company to report every month about the progress.
  • Commissioning date to remain uptill Dec., 2011

6

 Vill. Talwandi Rai, Tehsil Raikot, Distt. Ludhiana

14

24 Acre Panchayat land taken on lease.
IA signed on 24.12.2009 and PPA signed on 19.1.2010.

All statutory clearances obtained

Boundary pillers erected
Expected date of Commissionning in March. 2012

  • Asked company to achieve financial closure immediately
  • Company to report every month about the progress.
  • Commissioning date to remain uptill Dec., 2011

 

 

7

 Teh. & Distt. Barnala

10

MoU signed on 15.11.2007.

30 days termination notice given on 4.6.2010

Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied.
Expected date of Commissioning in jan. 2013

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010

 

Overall delay of 2 years 6 months approx. as on 31st August., 2010

Enhanced Security deposited.

Revised extension granted for 15 months completion by Sep., 10

8

 Tehsil Phillour, Distt. Jalandhar

10

MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied.. IA & PPA not signed
Expected date of Commissioning inFeb. 2013

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010
  • Project to be cancelled if no satisfactory progress.

9

Tehsil Shahkot, Distt. Jalandhar

10

MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied. IA & PPA not signed
. Expected date of Commissionning inOct. 2012

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010

10

,Teh & Distt. Bathinda

13.5

MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied. IA & PPA not signed
Expected date of Commissionning in March. 2012

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010

11

 Teh & Distt. Ludhiana

15

MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Panchayat resolution on 16.9.2008 pending with DDPO, Ludhiana for approval.
Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied. IA & PPA not signed
Expected date of Commissioning in August,  2012

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010

Overall delay of 2 years 6 months approx. as on 31st August., 2010

Enhanced Security deposited.

Revised extension granted for 15 months completion by Sep., 10

12

 Teh Sultanpur Lodhi, Distt. Kapurthala

9

MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied. IA & PPA not signed
Expected date of Commissionning in Dec. 2012

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010

 

13

 Teh & Distt. Fatehgarh Sahib

11

MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Panchayat Land lease of Vill. Bhoran pending due to litigation remarks on jamabandi : Thus, land agreement documents not submitted. DPR not submitted. Clearances yet to be applied. IA & PPA not signed
Expected date of Commissioning in July. 2012

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010

 

14

 Tehsil  Amloh & Distt. Fatehgarh Sahib

6

. MoU signed on 15.11.2007

30 days termination notice given on 4.6.2010

Land ownership/ lease agreement documents not submitted. DPR not submitted. Clearances yet to be applied.. IA & PPA not signed
Expected date of Commissionning in Nov. 2012

  • Project to be reviewed in Oct., 2010.
  • Asked company to have land by Oct., 2010
  • Project to be cancelled if no satisfactory progress.

 


M/S. Viaton Energy Pvt. Ltd. (formerly M/s  Food Fats & Fertilizers Pvt. Ltd, )

S.No.

Name of Site(Tehsil)

Capacity (MW)

Status

Decision taken in the meeting on 27.7.2010

Remarks

Actions completed                   Actions under Completion

1

  Vill. Khokhar Khurd,

Tehsil Mansa

20

Land ownership papers of 12.5 Acre submitted,
.MoU signed on 14.11.2007.
Financial closure achieved.

DPR submitted & approved .
Orders for boilers, turbogenerator, turbine were placed..
CLU approved.
Financial closure achieved.
SCA approval in progress.
IA & PPA yet to be signed
Expected date of Commissionning in March 2011

  • Company was asked to sign IA with in a week.
  • Company to start work for PPA with PowerCom.
  • Company was asked to commission the project by March, 2011.
  • Project to be reviewed by Oct., 2010.

Overall delay of 2 years 6 months approx. as on 31st August., 2010

Revised extension granted for 15 months completion by Sep., 10

M/S. P & R Engineering Services Ltd.

S.No.

Name of Site(Tehsil)

Cap. (MW)

Status

Decision taken in the meeting on 27.7.2010

Remarks

Actions completed                                          Actions under Completion

1

Anandpur Sahib

5

11 Acre Land ownership / Registration papers submitted
MoU signed on 14.11.2007
DPR approved.
30 days termination notice given on 4.6.2010

,. IA & PPA not signed
EIA clearance awaited.
Biomass Assessment Report submitted.

  • Project to be reviewed in Oct., 2010.
  • Company was asked to achieve financial closure.

Overall delay of 2 years 6 months approx.as on 31st August., 2010

Enhanced Security deposited.
Revised extension granted for 15 months completion by Sep., 10

2

Ropar

10

MoU signed on 14.11.2007.

  • 13 Acre Land ownership / Registration papers  submitted but Clarification sought from the company regarding river land
  • 30 days termination notice given on 4.6.2010
  • DPR, Biomass Assessment Report yet to be submitted.
  • IA & PPA not signed
  • Submit land papers within 15-20 days.
  • Project to be reviewed in Oct., 2010.
  • Project to be cancelled if no progress visible for Anandpur Sahib site.

3

 Nawanshahr

10

MoU signed on 14.11.2007

30 days termination notice given on 4.6.2010

DPR, Biomass Assessment Report &  Land papers yet to be submitted.
. IA & PPA not signed
Clearances yet to be applied.

  • Submit land papers within 15-20 days.
  • Project to be reviewed in Oct., 2010.
  • Project to be cancelled if no progress visible for Anandpur Sahib site.

 

M/s Orient Green Power Pvt. Ltd

S.No.

Name of site (Tehsil)

Cap. (MW)

Status

Decision taken in the meeting on 27.7.2010

Remarks

Actions completed                                          Actions under Completion

1

 Amritsar

10

  • 21 Acre Panchayat land lease agreement papers (Vill. Wadala Bhittiwaid) submitted.
  • Possession of land taken in Dec, 2009.
  • MoU signed on 14.11.2007
  • 30 days termination notice given on 4.6.2010
  • DPR submitted on 31.5.2010
  • . IA & PPA yet to be signed
  • Company was asked to achieve financial closure of the project.
  • Company was asked to show some substantial progress.
  • Progress to be submitted on monthly basis.
  • Project to be reviewed in Oct., 2010.

Overall delay of 2 years 6 months approx.as on 31st August., 2010

Enhanced Security deposited.

Revised extension granted for 15 months completion by Sep., 10

2.

 Patiala

10

MoU signed on 14.11.2007
30 days termination notice given on 4.6.2010

  • Land ownership/ lease agreement documents not submitted. DPR not submitted.
  • . IA & PPA not signed yet
  • Company to submit land papers by the end of Sep., 2010, otherwise project is cancelled.
  • Report to be submitted on monthly basis.

 

 